Basic Schedule of Decommissioning

  • process1
  • process2

The decommissioning scheduled to implement by dividing the period into four stages described below and will be completed until the fiscal 2040.

1.Heavy Water and Other system Decontamination Period

2.Reactor Periphery Facilities Dismantling Period

3.Reactor Dismantling Period

4.Building Demolition Period