Dismantling Work in Reactor Building

Dismantling Work on A-Loop Side (2019~2020)

The figure below shows the dismantling work of equipment and devices located on the A-loop side of the reactor cooling system inside the reactor building from 2019 to 2020. That was our 1st phase to dismantle the Reactor Periphery Facilities.
In this phase, we worked to accumulate experience and knowledge for the next step, the dismantling work on the B-loop side.

Dismantling Work on B-Loop Side (2020~2022)

At the dismantling work on the B-loop side is based on the experience and knowledge from work of the A-loop side,we have been proceeding with the dismantling work systematically by making various efforts such as safety measures and improving work efficiency.